SOLUTION: it takes an apprentice carpenter 2h longer to install a section of floor than it does a more experienced carpenter. After the carpenters work together for 2h. the experienced carpe
Question 973623: it takes an apprentice carpenter 2h longer to install a section of floor than it does a more experienced carpenter. After the carpenters work together for 2h. the experienced carpenter leaves for another job. It then takes the apprentice carpenter 2 h longer to complete the installation. How long would it take the apprentice, working alone, in install the floor Answer by josgarithmetic(39617) (Show Source):
You can put this solution on YOUR website! This is arranged as a uniform rates exercise, so you would assume (maybe incorrect in actual practice) that each person works according to his own rate.
1 job is, install a floor.
Person_____________Rate, job per hour
Apprentice__________
Experienced__________
Both together______
The process of these workers is both together for 2 hours, the apprentice alone for 2 more hours; and the job is finished.
RT=J for rate, time, job quantity. The sum of the work to be done will be 1 job.
.
Your algebra or arithmetic skills should be enough that you can solve the equation for x, which is the time for the experienced carpenter to do 1 job alone. You can then find x+2.