Question 990544: a crew of ten men take a week to overhaul 25 trucks in a fleet of 100 trucks. how many men would it take to complete the overhaul of the rest of the fleet the following week? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! 1 man would take 10 times as long to
overhaul the 25 trucks, so
1 man takes 10 weeks to overhaul 25 trucks
----------------------------------------
There are trucks left , so
1 man takes 30 weeks to overhaul 75 trucks
but it must be done in 1 week, so
30 men take 1 week to overhaul 75 trucks
( 30 times as many men will take 1/30 of the time )