SOLUTION: How do you solve a person-day problem? For example, "one man works 55 days to finish a job. How long will it take 5 men to do the same job all working at equal rates of speed?"
Algebra ->
Proportions
-> Lessons
-> SOLUTION: How do you solve a person-day problem? For example, "one man works 55 days to finish a job. How long will it take 5 men to do the same job all working at equal rates of speed?"
Log On
Question 827945: How do you solve a person-day problem? For example, "one man works 55 days to finish a job. How long will it take 5 men to do the same job all working at equal rates of speed?" Answer by Fombitz(32388) (Show Source):
You can put this solution on YOUR website! Rate*Time=Output
Let the work be done when the output reaches 1.
.
.
One man's rate is
Five men's rate would then be 5 times as much.
So then,
So it takes 5 men only 11 days to do the same job.