Question 421479
:
120 men can do a work in 90 days.How many more men are required to complete the work in 40 days?
Answer by
robertb(5830)
(
Show Source
):
You can
put this solution on YOUR website!
40(120 + x) = 120*90
==> 120 + x = 270
==> x = 150 more men needed to finish the work in 40 days.