SOLUTION: it required 75 men 38 days to build a flood control dike. if 18 less men were employed, how much longer would it have taken to build the dike? show the solution.
Algebra ->
Proportions
-> Lessons
-> SOLUTION: it required 75 men 38 days to build a flood control dike. if 18 less men were employed, how much longer would it have taken to build the dike? show the solution.
Log On
Question 344668: it required 75 men 38 days to build a flood control dike. if 18 less men were employed, how much longer would it have taken to build the dike? show the solution. Answer by Fombitz(32388) (Show Source):
You can put this solution on YOUR website! You need or man-days to complete the dike.
If you only have () men, then it would take, days to complete or () days longer.