...Assuming that all men work at the same rate,
Let the rate of 1 man be r.
5 men are hired to complete a job.
So the rate of the 5 men is 5r
Since time = production/rate = (1 job)/(5r),
The 5 men could do the job in 1/(5r) days
If one more man is hired,...
That makes 6 men, whose rate is 6r.
Since time = production/rate = (1 job)/(6r),
The 6 men could do the job in 1/(6r) days
the job can be completed 8days earlier.
So 1/(6r) is 8 days less than 1/(5t), or
1/(6r) = 1/(5r) - 8
Multiply thru by LCD = 30r
5 = 6 - 240r
-1 = -240r
1/240 = r <-- the rate of one man
That makes the rate of 5 men be 5/240,
or 1/48, that's 1 job per 48 days, so the
5 men could finish 1 job in 48 days.
how many more men should be hired so that
the job can be completed 28 days earlier
Let the number of men that must be hired be n
Then there will be 5+n men working
So the rate of 5+n men is (5+n)r = (5+n)(1/240) = (5+n)/240
Since time = production÷rate = (1 job)÷((5+n)/240) = 1×(240/(5+n) =
240/(5+n)
...the job can be completed 28 days earlier
So 240/(5+n) is 28 days less than the 48 days it would
take the 5 men, or 20 days.
240/(5+n) = 20
240 = 20(5+n)
240 = 100+20n
140 = 20n
7 = n
So 7 more men must be hired.
Edwin