Here are two more ways to do it:
The least common multiple of 15 men and 25 men is 75 men
If 15 men complete a work in 20 days
Then 5 times as many men, or 75 men, can do it in 1/5th the time, or 4 days
then 25 men will complete that work in how much days..?
25 men is 1/3rd of 75 men so it will take them 3 times as long, or 12 days.
---------------------
OR
---------------------
The greatest common factor of 15 men and 25 men is 5 men
If 15 men complete a work in 20 days
Then 1/3 as many men, or 5 men, will take 3 times as long, or 60 days
then 25 men will complete that work in how much days..
25 men is 5 times as many men as 5 men, so it will take them 1/5 as long,
or 12 days.
Edwin