| Question 805700:  if 8 workers take 6 hours to build a deck, how long will it take for 2 workers to do the same job?
 Found 2 solutions by  stanbon, MathTherapy:
 Answer by stanbon(75887)
      (Show Source): 
You can put this solution on YOUR website! if 8 workers take 6 hours to build a deck, how long will it take for 2 workers to do the same job? -------
 time/workers = time/workers
 -------
 t/2 = 6/8
 ---
 t = 2(3/4) = 6/4 = 1 1/2 hrs
 =============================
 Cheers,
 Stan H.
 ==================
Answer by MathTherapy(10556)
      (Show Source): 
You can put this solution on YOUR website! if 8 workers take 6 hours to build a deck, how long will it take for 2 workers to do the same job?
 
 
  hours 
 You can do the check!!
 
 Send comments, “thank-yous,” and inquiries to “D” at MathMadEzy@aol.com. Further help is available, online or in-person, for a fee, obviously.
 
 For FREE info and answers to questions about the ASVAB exam, the NYS 3 – 8 city/state wide exams, GENERAL MATH QUESTIONS, MATH HOMEWORK QUESTIONS, or MATH QUESTIONS related to the Regents Integrated Algebra, Regents Geometry, Regents Algebra 2/Trigonometry, SHSAT, COOP/HSPT/TACHS, PSAT, SAT, ACT, SSAT/ISEE, GRE, CLEP, and the GED, you can visit: http://asvabstudyzone.freeforums.net/.
 | 
  
 | 
 |