SOLUTION: It takes 12 people to complete a project in 36 days how many people is needed to complete the project in 24 days

Algebra ->  Test -> SOLUTION: It takes 12 people to complete a project in 36 days how many people is needed to complete the project in 24 days      Log On


   



Question 735589: It takes 12 people to complete a project in 36 days how many people is needed to complete the project in 24 days
Answer by ankor@dixie-net.com(22740) About Me  (Show Source):
You can put this solution on YOUR website!
It takes 12 people to complete a project in 36 days
Find how many man-days to complete the job
12 * 36 = 432 man-days to complete the job
:
how many people is needed to complete the project in 24 days
let m = no. of men require so complete in 24 days
24m = 432
m = 432/24
m = 18 men to do the job
:
:
You can also solve this with an inverse ratio equation
m%2F12 = 36%2F24
24m = 12*36
24m = 432
m = 432/24