Question 805700: if 8 workers take 6 hours to build a deck, how long will it take for 2 workers to do the same job?
Found 2 solutions by stanbon, MathTherapy: Answer by stanbon(75887) (Show Source):
You can put this solution on YOUR website! if 8 workers take 6 hours to build a deck, how long will it take for 2 workers to do the same job?
-------
time/workers = time/workers
-------
t/2 = 6/8
---
t = 2(3/4) = 6/4 = 1 1/2 hrs
=============================
Cheers,
Stan H.
==================
Answer by MathTherapy(10551) (Show Source):
You can put this solution on YOUR website!
if 8 workers take 6 hours to build a deck, how long will it take for 2 workers to do the same job?
hours
You can do the check!!
Send comments, “thank-yous,” and inquiries to “D” at MathMadEzy@aol.com. Further help is available, online or in-person, for a fee, obviously.
For FREE info and answers to questions about the ASVAB exam, the NYS 3 – 8 city/state wide exams, GENERAL MATH QUESTIONS, MATH HOMEWORK QUESTIONS, or MATH QUESTIONS related to the Regents Integrated Algebra, Regents Geometry, Regents Algebra 2/Trigonometry, SHSAT, COOP/HSPT/TACHS, PSAT, SAT, ACT, SSAT/ISEE, GRE, CLEP, and the GED, you can visit: http://asvabstudyzone.freeforums.net/.
|
|
|