Question 494362: It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the same rate to do the same job? Found 4 solutions by Maths68, MathTherapy, josgarithmetic, ikleyn:Answer by Maths68(1474) (Show Source):
You can put this solution on YOUR website! 4 men do a job in .14 days
Divide by 4 both sides
4/4 men do a job in .14/4 days
1 man does the same job in ..7/2 days
Multiply by 7 both sides
7*1 man does the same job in ..7*(7/2) days
7 men will do the same job in ..49/2 days
7 men will do the same job in ..24 ½ days
It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the same rate to do the same job?
************************************
The other person's answer, that it takes 7 men, 24 days to complete a job that 4 men take 14 days to do, makes ABSOLUTELY
no sense, especially seeing that both groups are working at the same rate. How can a larger group of men take MORE TIME
to a job than a smaller group, when both groups are working at the same rate? RIDICULOUS and NONSENSICAL!!
It'll take the 7 men to do the same job that it takes 4 men, 14 days to complete.
You can put this solution on YOUR website! .
It takes 4 men 14 days to do a certain job.
How long should it take 7 men working at the same rate to do the same job?
~~~~~~~~~~~~~~~~~~~~
This can be solved MENTALLY and MOMENTARILY.
(1) The whole job is 4 * 14 = 56 man-days.
(2) 7 men will make it in 56/7 = 8 days. ANSWER
Solved.
It is how my teachers taught us solving such problems 65 years ago.