Question 964216
:
if 8 men can do a job in 12 days how long will 24 men take to complete it
Answer by
amarjeeth123(569)
(
Show Source
):
You can
put this solution on YOUR website!
8 men can do a job in 12 days
24 men can do a job in 24*12/8=36 days.