Question 959377: Twelve men would take 15 days to finish a job if each works 8 hours a day. If this job has to be finished in 10 days,find the total number of extra hours that these 12 men must do altogether. Answer by macston(5194) (Show Source):
You can put this solution on YOUR website!
ANSWER: The men must work 12 hrs/day to finish in 10 days.
ANSWER: The men must work a total of 480 extra hours.