Question 809610
:
If 18 workers sew 540 dresses in 6 weeks,how long would it take 12 workers to do?
Answer by
richwmiller(17219)
(
Show Source
):
You can
put this solution on YOUR website!
18*6=108 worker weeks
540/108=5 dresses per worker week.
108/12=9 weeks