SOLUTION: I have 1324 hours to work on project from August 1st until the end of December. So far I have been on the project for 4 weeks. I must spend 60 hours each week working on this proje

Algebra ->  Equations -> SOLUTION: I have 1324 hours to work on project from August 1st until the end of December. So far I have been on the project for 4 weeks. I must spend 60 hours each week working on this proje      Log On


   



Question 484845: I have 1324 hours to work on project from August 1st until the end of December. So far I have been on the project for 4 weeks. I must spend 60 hours each week working on this project. As of today whats the percentage I have completed on this project?
Answer by nerdybill(7384) About Me  (Show Source):
You can put this solution on YOUR website!
I have 1324 hours to work on project from August 1st until the end of December. So far I have been on the project for 4 weeks. I must spend 60 hours each week working on this project. As of today whats the percentage I have completed on this project?
(4*60)/1324 * 100
240/1324 * 100
0.18 * 100
18%