Can you help me solve this problem?
Julio works as a quality control expert in a beverage factory. The assembly line that he monitors produces about 20,000 bottles in a 24-hour period. Julio samples about 120 bottles an hour and rejects the line if he finds more than 1/50 of the sample to be defective. About how many defective bottles should Julio allow before rejecting the entire line?
Thanks!

Answer by fractalier(6550) About Me  (Show Source):
You can put this solution on YOUR website!
I posted this solution a few days ago...please scroll down thru my work to find it...I think he could allow two defective bottles at most before rejecting the whole lot...