Questions on Word Problems: Rate of work, PAINTING, Pool Filling answered by real tutors!

Algebra ->  Rate-of-work-word-problems -> Questions on Word Problems: Rate of work, PAINTING, Pool Filling answered by real tutors!      Log On


   



Tutors Answer Your Questions about Rate-of-work-word-problems (FREE)


Question 850681: A machine P can print one math book in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one math book) be finished ?
Answer by MathTherapy(10806) About Me  (Show Source):
You can put this solution on YOUR website!
A machine P can print one math book in 8 hours, machine Q can print the same number of 
books (this author believes this should be PAGES) in 10 hours while machine R can print them in
12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the
remaining two machines complete work. Approximately at what time will the work (to print one
math book) be finished ?
***************************************************************
The other person's answer, "approximately" 12:03 PM....", is WRONG!!

Machine P does the job (prints book) in 8 hrs, or does %281%2F8%29%5E%28th%29 of entire job in 1 hr

Machines P and Q do the job (print book) in 10 and 12 hrs, respectively
Then each does %281%2F10%29%5E%28th%29 and %281%2F12%29%5E%28th%29 of entire job in 1 hr, respectively

In 2 hours, the 3 machines complete 2%281%2F8+%2B+1%2F10+%2B+1%2F12%29 = 2%2F8+%2B+2%2F10+%2B+2%2F12 = 1%2F4+%2B+1%2F5+%2B+1%2F6 = %2815+%2B+12+%2B+10%29%2F60 = 37%2F60

Let the time it takes Q and R to complete the job, be T
Then working together, Q and R completes T%281%2F10+%2B+1%2F12%29 of the job

We then get the following COMPLETE-JOB equation: T1(rates) + T2(rates) = 1 (entire job), OR
                                        Fraction completed + Remaining Fraction = 1 (entire job). This produces: 
                                                        37%2F60+%2B+T%281%2F10+%2B+1%2F12%29+=+1
                                                           37%2F60+%2B+T%2F10+%2B+T%2F12+=+1
                                                          37 + 6T + 5T = 60 ---- Multiplying by LCD, 60
                                                              37 + 11T = 60
                                                                   11T = 60 - 37
                                                                   11T = 23
Time it takes Q and R to complete the job, after P, Q, and R worked together for 2 hrs, or matrix%281%2C2%2C+T+=+23%2F11+=+2%261%2F11%2C+hrs%29
or 2 hrs, 5.5 minutes, approximately.


Finally, 2 hrs, 5.5 minutes after 11:00 a.m. takes us to 1:05.5, or approximately 1:06 p.m.


ANECDOTE
As seen above, the other person's approximated 1-hr claim is INVALID. The 3 machines completed 37%2F60 of job in 2
hours, which leaves 23%2F60 of the job, incomplete. Does it make sense that 3 machines take 2 hours to complete 37%2F60,
or > 1%2F2 of the job, but 2 of the 3 machines take just 1 hour to complete the remaining 1%2F3 (approximation),
especially when the FASTEST of the 3, P, is no longer working?


Question 1002869: The Department ot Education is holding their annual Brigada Eskwela to prepare and clean up the classrooms.Kimberly can paint a chair in 45 minutes.Arthur can paint the same chairs in 30 minutes. If they work together, how long will it take them to paint six chairs.
Found 5 solutions by math_tutor2020, greenestamps, josgarithmetic, n2, ikleyn:
Answer by math_tutor2020(3835) About Me  (Show Source):
You can put this solution on YOUR website!

Let's say for a hypothetical argument that each chair's surface area is 900 square inches.
As it turns out, this figure 900 doesn't matter since you can change it to any positive real number you want. The final answer at the end will remain the same.


Kimberly can paint one chair (900 square inches) in 45 minutes, so her unit rate is 20 square inches per minute because:
rate = amountDone/time = 900/45 = 20 square inches per minute


Meanwhile,
Arthur's unit rate = 900/30 = 30 square inches per minute

When the two work together, the combined unit rate would be 20+30 = 50 square inches per minute.
This assumes neither person slows the other down.

1 chair has 900 square inches of material.
6 chairs cover 6*900 = 5400 square inches

rate*time = amountDone
time = amountDone/rate
time = 5400/50
time = 108 minutes
time = 60 min + 48 min
time = 1 hr + 48 min


Answer: 108 minutes (i.e. 1 hour & 48 minutes)

Side note: The answer by mananth applies to 1 chair. You have to multiply 18 by 6 to get the time duration for 6 chairs.

Answer by greenestamps(13327) About Me  (Show Source):
You can put this solution on YOUR website!


All of the responses you have received so far use the same formal algebraic method that is found in most textbooks, using fractions of the job performed by each worker each minute.

Here is a less formal way of solving this kind of problem; this method can be a lot faster than the formal algebraic method, especially if the numbers are "nice".

Consider the least common multiple of the two given times, which is 90 minutes. In 90 minutes...
the number of chairs Kimberly can paint is 90/45 = 2
the number of chairs Arthur can paint is 90/3 = 3
the number of chairs they can paint together is 2+3 = 5

They can paint 5 chairs in 90 minutes, so the number of minutes it takes them to paint each chair is 90/5 = 18.

So the time required for them to paint 6 chairs is 18*5 = 108 minutes

ANSWER: 108 minutes


Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
                RATE              TIME         CHAIRS

Kimberly        1/45              45             1

Arthur          1/30              30             1

Combined       1/45+1/30           t            6

For the combined rate, the expression, best denominator to use should be 90.
2%2F90%2B3%2F90=5%2F90=highlight_green%281%2F18%29 when reduced.

%281%2F18%29t=6
t=18%2A6
highlight%28t=108%29

Answer by n2(79) About Me  (Show Source):
You can put this solution on YOUR website!
.
The Department of Education is holding their annual Brigada Eskwela to prepare and clean up the classrooms.
Kimberly can paint a chair in 45 minutes. Arthur can paint the same highlight%28cross%28chairs%29%29 chair in 30 minutes.
If they work together, how long will it take them to paint six chairs.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


The whole job is to paint 6 chairs (not one chair but six of them).


Kimberly can make this job in 30*6 = 180 minutes; hence, Kimberly makes 1/180 of the job per minute.

Arthur   can make this job in 45*6 = 270 minutes; hence, Kimberly makes 1/270 of the job per minute.


Working together, they make  

    1%2F180 + 1%2F270 = 3%2F540 + 2%2F540 = 5%2F540 = 1%2F108


of the job per minute.


Hence, they need 108 minutes, or 1 hour and 48 minutes to complete the job working together.    ANSWER

At this point, the problem is solved completely.



Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
The Department of Education is holding their annual Brigada Eskwela to prepare and clean up the classrooms.
Kimberly can paint a chair in 45 minutes. Arthur can paint the same highlight%28cross%28chairs%29%29 chair in 30 minutes.
If they work together, how long will it take them to paint six chairs.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution and the answer in the post by @mananth are catastrophically wrong.
        Trace attentively my solution below,  and you will find,  where @manant did his fatal error.


The whole job is to paint 6 chairs (not one chair but six of them).


Kimberly can make this job in 30*6 = 180 minutes; hence, Kimberly makes 1/180 of the job per minute.

Arthur   can make this job in 45*6 = 270 minutes; hence, Kimberly makes 1/270 of the job per minute.


Working together, they make  

    1%2F180 + 1%2F270 = 3%2F540 + 2%2F540 = 5%2F540 = 1%2F108  of the job per minute.


Hence, they need 108 minutes, or 1 hour and 48 minutes to complete the job working together.      ANSWER

At this point, the problem is solved completely and correctly.




Question 1027961: A takes 10 days less than the time taken by B to finish an embroidery work. If both A and B together can finish the work in 12 days. Find the time taken by B alone to finish the work.
Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
Workrate for A, 1%2F%28b-10%29
Workrate for B, 1%2Fb
Rate of A and B together, 1%2F12

Meaning 1%2F12=1%2F%28b-10%29%2B1%2Fb. Solve for b.

That should become b%5E2-34b%2B120=0.
Two numbers will occur for b, but the realistic result is highlight%28b=30%29.

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.

In the post by @mananth, the solution to the problem is correct,
but the answer presented in his post is wrong.


The correct answer is

        A takes 20 days
        B takes 30 days to do the job alone




Question 1029990: A container 80cm/60cm/70cm needs to be filled up completely with water. Tube A supplies 24l of water per minute and Tube B supplies 18l of water per minute. Mr Tan fills up the container by taking turns to use both Tubes for 17minutes. How long does he use each of the Tubes?
Found 2 solutions by n2, ikleyn:
Answer by n2(79) About Me  (Show Source):
You can put this solution on YOUR website!
.
A container 80cm/60cm/70cm needs to be filled up completely with water.
Tube A supplies 24l of water per minute and Tube B supplies 18l of water per minute.
Mr Tan fills up the container by taking turns to use both Tubes for 17minutes.
How long does he use each of the Tubes?
~~~~~~~~~~~~~~~~~~~~~~~~~~~


The volume of the tank is 80*60*70 = 336000 cm^3,  or 336 liters.

Let x be the time for tube A working, in minutes;

then (17-x) is the time for the tube B working.


Write an equation for the total volume

    24*x + 18*(17-x) = 336.


Simplify and find x

    24x + 306 - 18x = 336

    24x - 18x = 336 - 306

        6x    =    30

         x    =    30/6 = 5.


So, tube A worked 5 minutes;  tube B worked 17-5 = 12 minutes.    <<<---===  ANSWER


CHECK.  The total volume is  24*5 + 18*12 = 336 liters,  which is precisely correct.

Solved.



Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
A container 80cm/60cm/70cm needs to be filled up completely with water.
Tube A supplies 24l of water per minute and Tube B supplies 18l of water per minute.
Mr Tan fills up the container by taking turns to use both Tubes for 17minutes.
How long does he use each of the Tubes?
~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution in the post by @mananth is  FATALLY  INCORRECT.

        It is incorrect,  because his setup equations are irrelevant to the problem.

        I came to bring a correct solution.


The volume of the tank is 80*60*70 = 336000 cm^3,  or 336 liters.

Let x be the time for tube A working, in minutes;

then (17-x) is the time for the tube B working.


Write an equation for the total volume

    24*x + 18*(17-x) = 336.


Simplify and find x

    24x + 306 - 18x = 336

    24x - 18x = 336 - 306

        6x    =    30

         x    =    30/6 = 5.


So, tube A worked 5 minutes;  tube B worked 17-5 = 12 minutes.    <<<---===  ANSWER


CHECK.  The total volume is  24*5 + 18*12 = 336 liters,  which is precisely correct.

Solved correctly.

This situation is  100%  typical.

@mananth uses a computer code,  which generates solutions for his problems.
If a problem is one step from a standard,  the code produces gibberish,
but @mananth's reaction is zero - he  NEVER  reads what his code does produce:
he submits it to the forum without reading it,  without checking and without looking at it.

It is why every his post should be checked by others and it is why I check as many of them as I can.




Question 1038207: Paul can do a certain job in half the time that Jim requires to do it. Jim worked alone for an hour and stopped; then Paul completed the job in 10 hours. What length of time, in hours, would Paul, working alone, take to do the whole job?
Found 4 solutions by KMST, josgarithmetic, n2, ikleyn:
Answer by KMST(5345) About Me  (Show Source):
You can put this solution on YOUR website!
Jim worked alone for 1 hour and stopped.
Paul comes in, sees the work Jim did in 1 hour and says
"It would have taken me 1%2F2 to do that. I do any job in half the time it takes Paul to do it"
After Paul worked another 10 hours, the job was finished.
Then Jim said "SEE!, I could have done the whole thing in 10%2B1%2F2=highlight%2810.5%29 hours. I may only have a fourth-grade education, but I can work twice as fast as Paul, without knowing what algebra is about."

The problem with mananth solution seems to be that after getting to
((x-1)/x)/(2/x)=10 or %28%28x-1%29%2Fx%29%2F%282%2Fx%29=10 mananth apparently thought
"I could simplify the left side expression by writing it as %28%28x-1%29%2Fx%29%28x%2F2%29 because dividing by 2%2Fx is multiplying times x%2F2 to end with %28x-1%29%2Fx on the left and a simple expression on the right.
or I could simplify the equation by multiplying both sides by 2%2Fx"
Then mananth had one of those brain-farts and multiplied the left hand side times 2%2Fx and the right hand side times x%2F2 ending with %28x-1%29%2Fx on the left and 10%28x%2F2%29=5x on the right.
Keeping the equal sign in between, mananth concluded that Jim could have done the whole job in 2 hours, forgetting that it took Jim 10 hours to do part of the job.
We we all have one of those brain farts now and then. One professor told about answering a problem on a radio station show by saying that the top of an 8 foot ladder leaning again the side of a house would be 10 feet above the ground.

Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
https://www.algebra.com/algebra/homework/Linear-equations/Linear-equations.faq.question.1106092.html

Answer by n2(79) About Me  (Show Source):
You can put this solution on YOUR website!
.
Paul can do a certain job in half the time that Jim requires to do it.
Jim worked alone for an hour and stopped; then Paul completed the job in 10 hours.
What length of time, in hours, would Paul, working alone, take to do the whole job?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


Let 'a' be the Jim's rate of work, i.e. part of work, which Jim makes in 1 hour.

Then the Paul's rate of work is 2a, according to the problem.


Jim worked alone for an hour and stopped; then Paul completed the job in 10 hours. 


It means that

    a + 10*(2a) = 1,    where '1' represents the whole job.


From this equation, we find

    a + 20a = 1  --->  21a = 1  --->  a = 1/21.


It means that Jim makes 1/21 of the Job per hour.
In other words, Jim needs 21 hours to make the whole job alone.

Hence, according to the problem, Paul needs half of 21 hours to make the whole job alone.

In other words, Paul needs 21/2 = 10.5 hours to make the whole job alone.    ANSWER



Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
Paul can do a certain job in half the time that Jim requires to do it.
Jim worked alone for an hour and stopped; then Paul completed the job in 10 hours.
What length of time, in hours, would Paul, working alone, take to do the whole job?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution by @mananth to this problem is INCORRECT.
        It is obvious if to compare his answer with the given data in the problem.

        I came to bring a correct solution.


Let 'a' be the Jim's rate of work, i.e. part of work, which Jim makes in 1 hour.

Then the Paul's rate of work is 2a, according to the problem.


Jim worked alone for an hour and stopped; then Paul completed the job in 10 hours. 


It means that

    a + 10*(2a) = 1,    where '1' represents the whole job.


From this equation, we find

    a + 20a = 1  --->  21a = 1  --->  a = 1/21.


It means that Jim makes 1/21 of the Job per hour.
In other words, Jim needs 21 hours to make the whole job alone.

Hence, according to the problem, Paul needs half of 21 hours to make the whole job alone.

In other words, Paul needs 21/2 = 10.5 hours to make the whole job alone.    ANSWER

At this point, the problem is solved completely and correctly.


-------------------------


What we observe in this case, is very typical situation.

The solution by @mananth was created by a computer code - which was a prototype of an Artificial Intelligence in its current state.

As soon as this code met a non-standard formulation, it produced wrong solution (= kind of gibberish).

Not only it produced wrong solution - it even did not check it, even did not notice it and even did not react
on wrong solution.

It shows, that the AI is in its infantile state and can work properly only if real persons and experts
accompany its work, checking every step.




Question 394478: A piece of work can be done in 48 days by 40 men. After 15 days, 16 men were transferred. In how many days can the remaining men finish the work?
Found 2 solutions by ikleyn, MathTherapy:
Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
A piece of work can be done in 48 days by 40 men. After 15 days, 16 men were transferred.
In how many days can the remaining men finish the work?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        Below is simple arithmetic solution, without using Algebra.


The entire job is 40 men * 48 days = 1920 man-days.

40 men, working 15 days, used 40*15 = 600 man-days.


The remaining job is 1920-600 = 1320 man-days.


Now only 40-16 = 24 men work.


They will complete the remaining job in  1320/24 = 55 days.    <<<---===  ANSWER

Solved.



Answer by MathTherapy(10806) About Me  (Show Source):
You can put this solution on YOUR website!
A piece of work can be done in 48 days by 40 men. After 15 days, 16 men were transferred. In how many days
can the remaining men finish the work?
**************************************
79.375 days, by one of the persons who responded, is WRONG!! The other person's answer is correct, but for 55 days, not
the 55 hours he posted!


Question 1154714: Howard and Edward, working together, can complete a job in 12 hours. Edward requires 18 hours to do this job alone. Howard and Edward start the job. After they worked for 4 hours, Howard left the job. How many hours will Edward require to finish the job working alone?
Found 2 solutions by josgarithmetic, ikleyn:
Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
h, time for Howard alone to do one job
18, time for Edward to do one job

First two sentences
1%2Fh%2B1%2F18=1%2F12
1%2Fh=1%2F12-1%2F18
36%2Fh=36%281%2F12-1%2F18%29
36%2Fh=3-2
36%2Fh=1
highlight_green%28h=36%29

Last three sentences
x, how many hours Edward worked alone to finish job
(No need to know h)
%281%2F12%29%2A4%2B%281%2F18%29x=1
1%2F3%2Bx%2F18=1
6%2Bx=18
highlight%28x=12%29

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
Howard and Edward, working together, can complete a job in 12 hours. Edward requires 18 hours to do this job alone.
Howard and Edward start the job. After they worked for 4 hours, Howard left the job. How many hours will Edward
require to finish the job working alone?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution in the post by @mananth is incorrect.
        Below is my correct solution.


Edward requires 18 hours to do this job alone.

He does 1/18 of job in 1 hour

Howard and Edward start the job they worked for 4 hours,

They can complete the job in 12 hours

So they can do 1/12 of the job in 1 hour

they worked for 4 hours

so they completed 4/12 of the job = 1/3 of the job

The remaining job is 1-1/3 = 2/3 of the job

Edward does 1/18 of job in 1 hour

for 1/3 of the job he will take %28%282%2F3%29%29%2F%28%281%2F18%29%29 hours = %282%2A18%29%2F3 = 36%2F3 = 12 hours.

ANSWER.   Edward will take 12 hours to complete the job.


Solved correctly.




Question 1081944: 80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the 45th day, 10 men were hired. How many days were they delayed finishing the job.
Found 3 solutions by ikleyn, math_tutor2020, MathTherapy:
Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the 45th day,
10 men were hired. How many days were they delayed finishing the job.
~~~~~~~~~~~~~~~~~~~~~~~~~~~


        I will show you the method, which you (i hope) will remember for all your life.


(1)  The entire job is 80 men * 60 days = 4800 man-days.



(2)  80 men worked first 15 day and used 80 * 15 = 1200 man-days.

     The remaining job is 4800 - 1200 = 3600  man days.



(3)  Then (80-5) = 75 men worked from the day 16th till the day 44th inclusively, i.e. 44-15 = 29 days.

     They used 75 * 29 = 2175 man-days, and 3600 - 2175 = 1425 man-days work remained.



(4)  Starting from the 45th day, 75+10 = 85 men work.

     They complete the remaining job in  1425/85 = 16.7647 days, approximately.



(5)  So, the number of days they worked to complete the job is  15 + 29 + 16.7647 = 60.7647.    ANSWER


You can round it in a way you want.

Solved and explained.


            Counting man-days (or man-hours, or man-minutes)
            is a powerful method solving rate-of-work problems.



Answer by math_tutor2020(3835) About Me  (Show Source):
You can put this solution on YOUR website!

Let's say hypothetically that the job is to move 9600 stones.
I got this value by multiplying the numbers in the first sentence, then doubling the result.
It turns out that this value can be changed to any thing else you want; the final answer at the end will be the same. I picked 9600 so that I would get an integer when dividing in the next paragraph.

9600 stones
80 men
9600/80 = 120 stones per person
Each person is responsible for moving 120 stones. Each person can do it in 60 days, so the rate is 120/60 = 2 stones per day.

At the end of the 15th day, each person has moved 15*2 = 30 stones.
So that is 80*30 = 2400 stones that have been moved so far.
There are 9600-2400 = 7200 stones remaining.

5 men are laid off, so there are 80-5 = 75 men remaining.
The time gap from day 16 to day 44 is 44-16+1 = 29 days.
In those 29 days, 75 men move 75*2*29 = 4350 stones
7200-4350 = 2850 stones remain at the end of day 44.

On day 45, there are 10 new workers to bring the count to 75+10 = 85 workers.

x = number of days to move the remaining stones
85*2*x = 170x = number of stones to move
170x = 2850
x = 2850/170
x = 285/17
x = 16.765 approximately

44+x = 44+16.765 = 60.765 days (roughly) is the time it takes for the entire job to be completed.
This rounds to roughly 61 days.
This is in contrast to the estimated 60 day window.
61-60 = 1 is the amount they go over.


Answer: Approximately 1 day late

Answer by MathTherapy(10806) About Me  (Show Source):
You can put this solution on YOUR website!
80 men can finish the job in 60 days. At the 16th day, 5 men were laid off and at the 45th day, 10 men were hired.
How many days were they delayed finishing the job.
**************************************************
7+-day delay, from the other person is WRONG!!

80-MAN rate: 1%2F60
1-MAN rate: 1%2F%2880%29%2860%29+=+1%2F%224%2C800%22
75-MAN rate: 75%281%2F%224%2C800%22%29+=+1%2F64
85-MAN rate: 85%281%2F%224%2C800%22%29+=+17%2F960

Number of days the full crew (80 men) worked: 15 (day 1 to day 15)
Number of days 5 less, or 75 (80 - 5) men worked: 29 (day 16 to day 44)
Number of days 10 more, or 85 (75 + 10) men worked: Unknown, or T

We then get: T1(rate) + T2(rate) + T3(rate) = 1
                  15%281%2F60%29+%2B+29%281%2F64%29+%2B+T%2817%2F960%29+=+1
                                 1%2F4+%2B+29%2F64+%2B+17T%2F960+=+1
                      1(240) + 29(15) + 17T = 960 -- Multiplying by LCD, 960
                            240 + 435 + 17T = 960
                                  675 + 17T = 960
                                        17T = 960 - 675 
                                        17T = 285
Time taken by the final 85-man crew, to complete remaining fraction of job, or T = 285%2F17 = 16%2613%2F17, or about 17 days 

So, entire job took 15 + 29 + 17 = 61 days, which was 1 day over the 60-day deadline.


Question 773494: A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to another job. how many more days will the remaining men finish the job?
Found 3 solutions by ikleyn, josgarithmetic, MathTherapy:
Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to another job.
how many more days will the remaining men finish the job?
~~~~~~~~~~~~~~~~~~~~~~~~~~~


        I will show another way to solve, using different method.

        Its advantage is that the fractions or equations are not used.


The total job is 5 men * 10 days = 50 man-days.


In the first 4 days, 5 men used 5*4 = 20 man-days;  50 - 20 = 30 man-days work remained.


Now only 5 - 3 = 2 men work.  They need 30/2 = 15 days to complete the remaining job.


So, the remaining 2 men will finish the rest of the job in 15 days.    <<<---===  ANSWER

Solved completely, using mental reasoning instead equations and/or fractions.



Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
r, the work rate of 1 man
For 5 men working 10 days to do 1 "piece of work"
5r%2A10=1
or
r=1%2F50

Five men worked for 4 days and then 2 men worked for some x days to finish.
highlight_green%285%281%2F50%29%2A4%2B2%281%2F50%29x=1%29
5%2A4%2B2x=50
2x=50-20
2x=30
highlight%28x=15%29

Answer by MathTherapy(10806) About Me  (Show Source):
You can put this solution on YOUR website!
A piece of work can be done by 5 men in 10 days. After 4 days, 3 men were transferred to another job. how many more
days will the remaining men finish the job?
=======================================================
What the other person has for an answer makes absolutely NO SENSE. How can it take 2 men, just 6 days to complete a job that
a group of 5 men, who normally take 10 days to complete the job, worked for 4 days, and then left the 2 men to complete? 

5-MAN rate: 1%2F10
1-MAN rate: 1%2F%285%29%2810%29+=+1%2F50
2-MAN rate: 2%281%2F50%29+=+2%2F50+=+1%2F25

Formula: (Time 1 * rate 1) + Time 2 * rate 2) = 1 (entire job)
                               4%281%2F10%29+%2B+T%281%2F25%29+=+1
                                       2%2F5+%2B+T%2F25+=+1
                                      10 + T = 25 ---- Multiplying by LCD, 25 

Time taken for remaining 2 men to complete job, or T = 25 - 10 = 15 days


Question 1179401: . Peter and Steven take 5 1/3 hours to do a job. Steven alone takes 16 hours to
do the same job. How long would it take Peter to do the same job alone?

Answer by n2(79) About Me  (Show Source):
You can put this solution on YOUR website!
.
Peter and Steven take 5 1/3 hours to do a job. Steven alone takes 16 hours to do the same job.
How long would it take Peter to do the same job alone?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution in the post by @mananth is incorrect.
        As I say sometimes,  it is  TOTALLY  and  FATALLY  wrong.
        I came to bring a standard and correct solution to the problem.


Working together, Peter and Steven take  5 1/3 = 16%2F3  hours to make the job.

Hence, they make  1%2F%28%2816%2F3%29%29 = 3%2F16  of the job per hour.


In other words, their combined rate of work is  3%2F16.


Steven alone makes  1%2F16  of the job per hour.


Hence, Peter alone makes  3%2F16 - 1%2F16 = 2%2F16 = 1%2F8  of the job per hour.


It means that Peter needs 8 hour to complete the job working alone.   <<<---===  ANSWER

At this point, the problem is solved completely.




Question 1179655: The bird capable of the fastest flying speed is the swift. A swift flying with the wind to a favorite feeding spot traveled 42 mi in 0.3 h. On returning, now against the wind, the swift was able to travel only 27 mi in the same amount of time. What is the rate of the swift in calm air, and what was the rate of the wind?
Found 2 solutions by n2, ikleyn:
Answer by n2(79) About Me  (Show Source):
You can put this solution on YOUR website!
.
The bird capable of the fastest flying speed is the swift. A swift flying with the wind to a favorite feeding spot
traveled 42 mi in 0.3 h. On returning, now against the wind, the swift was able to travel only 27 mi
in the same amount of time. What is the rate of the swift in calm air, and what was the rate of the wind?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


Let x be the rate of the swift in calm air, in miles per hour.

Let y be the rate of the wind.


Then  the effective speed of the swift with    the wind is (x+y) mph,

while the effective speed of the swift against the wind is (x-y) mph,



From the problem, the effective rate of the swift with the wind is  the distance divided by the travel time

    42%2F0.3 = 140 miles per hour,


and the effective rate of the plane against the wind is  the distance divided by the travel time

    27%2F0.3 = 90 miles per hour.


So, we have these two equations

    x + y = 140     (1)

    x - y =  90     (2)


To find x, add the equation.  You will get

    2x = 140 + 90 = 230,  x = 230/2 = 115.


Now express y from equation (1) and calculate

    y = 140 - x = 140 - 115 = 25.


At this point the problem is solved completely.


ANSWER.  The speed of the swift in calm air is  115 mph.  The rate of the wind is 25 mph.

Solved correctly.



Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
The bird capable of the fastest flying speed is the swift. A swift flying with the wind to a favorite feeding spot
traveled 42 mi in 0.3 h. On returning, now against the wind, the swift was able to travel only 27 mi
in the same amount of time. What is the rate of the swift in calm air, and what was the rate of the wind?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution to this problem in the post by @mananth is INCORRECT.
        It is incorrect due to arithmetic error in his calculations.
        In this my post, I provide short, correct and straightforward solution to the given problem.


Let x be the rate of the swift in calm air, in miles per hour.

Let y be the rate of the wind.


Then  the effective speed of the swift with    the wind is (x+y) mph,

while the effective speed of the swift against the wind is (x-y) mph,



From the problem, the effective rate of the swift with the wind is  the distance divided by the travel time

    42%2F0.3 = 140 miles per hour,


and the effective rate of the plane against the wind is  the distance divided by the travel time

    27%2F0.3 = 90 miles per hour.


So, we have these two equations

    x + y = 140     (1)

    x - y =  90     (2)


To find x, add the equation.  You will get

    2x = 140 + 90 = 230,  x = 230/2 = 115.


Now express y from equation (1) and calculate

    y = 140 - x = 140 - 115 = 25.


At this point the problem is solved completely.


ANSWER.  The speed of the swift in calm air is  115 mph.  The rate of the wind is 25 mph.

Solved correctly.


-------------------------------


The solution by @mananth is defective, since it contains arithmetic errors.

It is also defective methodically, since it contain excessive unnecessary calculations.

We, the tutors, write here our solutions not only to get certain numerical answer.
We write to teach - and, in particular, to teach solving in right style.

This style solving presented in my post, is straightforward with no logical loops.
The solution presented in the post by @mananth has two logical loops.

One loop in the @mananth post is writing

    d/r = t  --->  42/(x+y) = 0.3   --->   0.3x + 0.3y = 42  --->  /0.3  --->  x+y = 42/0.3 = 140,

while in my solution I simply write for the effective rate 

    u + v = 42/0.3 = 140.


Second loop in the @mananth post is writing

                   27/(x-y) = 0.3   --->   0.3x - 0.3y = 27  --->  /4  --->  x-y = 27/0.3 = 60  (error: must be 90),

while in my solution I simply write for the effective rate upstream

    u - v = 27/0.3 = 90.

It is why I presented my solution here and why I think it is better than the solution by @mananth:
- because it teaches students to present their arguments in a straightforward way, without logical zigzags.

@mananth repeats his construction of solution with no change for all similar problems on flies
with and against the wind simply because his COMPUTER CODE is written this way.
But this way is not pedagogically optimal - in opposite, it is pedagogically imperfect.





Question 1181303: Carlo can type a manuscript for 10 hours. he started working then bobby joined him 2 hours later. they worked together for 4 hrs until carlo decided to stop and then bobby had to finish the manuscript alone. if bobby finished the remaining portion in 6 more hours, how long can he type the whole manuscript working alone?
Found 4 solutions by CPhill, greenestamps, MathTherapy, ikleyn:
Answer by CPhill(2189) About Me  (Show Source):
You can put this solution on YOUR website!
Consider typing a manuscript is 1 job
Carlo takes 10 hours to do the job alone
So he does 1/10 of the job in 1 hour
in the first two hours he does 2/10 of the job ------------A
let bobby take x hours to do the job alpne
so he does 1/x of the job in 1 hour
together they do (1/10 +1/x ) of the job in 1 hour
they work together for4 hours.
so they do 4 (1/10 + 1/x ) job = 4(10+x)/10x = 2(10+x)/5x of the job-----B
Booby works for 6 hours
so he does 6/x of the job -------------C
A+B+c = 1 job
2/10 + 2(10+x)/5x + 6/x =1
Solve for x

Answer by greenestamps(13327) About Me  (Show Source):
You can put this solution on YOUR website!


Carlo worked for 2 hours alone and then 4 hours with Bobby, for a total of 6 hours. Since he can do the whole job in 10 hours, the fraction of the job that he did is 6/10 = 3/5.

So Bobby did 2/5 of the job. He worked for 4 hours with Carlo and then 6 more hours alone, for a total of 10 hours.

Since he did 2/5 of the job in 10 hours, the amount of time it would take him to do the job alone is 10%2F%282%2F5%29=10%2A%285%2F2%29=25

ANSWER: 25 hours


Answer by MathTherapy(10806) About Me  (Show Source):
You can put this solution on YOUR website!
Carlo can type a manuscript for 10 hours. he started working then bobby joined him 2 hours later. they worked together for 4 hrs
until carlo decided to stop and then bobby had to finish the manuscript alone. if bobby finished the remaining portion in 6 more
hours, how long can he type the whole manuscript working alone?

Carlo can complete the job in 10 hours, or 1%2F10 of job in 1 hr
Let time Bobby takes, to do entire job, by himself, be B
Then, Bobby can complete 1%2FB of job in 1 hr

Since Bobby started 2 hours after Carlo, then Carlo worked alone for 2 hours. So, fraction of job completed by Carlo,
before Bobby joined him = 2%281%2F10%29+=+2%2F10
With both working together for 4 hrs, fraction of job both completed, working together = 4%281%2F10+%2B+1%2FB%29
Finally, given that Bobby completed the remaining portion in 6 hours, fraction of entire job done by Bobby, alone, = 6%281%2FB%29. 
We then get the following ENTIRE JOB-equation: 2%2F10+%2B+4%281%2F10+%2B+1%2FB%29+%2B+6%281%2FB%29+=+1
                                                       2%2F10+%2B+4%2F10+%2B+4%2FB+%2B+6%2FB+=+1
                                                            6%2F10+%2B+10%2FB+=+1
                                                          6B + 100 = 10B ----- Multiplying by LCD, 10B
                                                               100 = 10B - 6B
                                                               100 = 4B
Time taken by Bobby to do the ENTIRE job, working ALONE, or 

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
Carlo can type a manuscript for 10 hours. He started working then Bobby joined him 2 hours later.
they worked together for 4 hrs until Carlo decided to stop and then Bobby had to finish the manuscript alone.
if Bobby finished the remaining portion in 6 more hours, how long can he type the whole manuscript working alone?
~~~~~~~~~~~~~~~~~~~~~~~~


        To this problem, I will give two solutions:  first  Arithmetic and the second  Algebra.


                Arithmetic solution


Carlo's rate of work is 1/10 of the job per hour.

Carlo typed 2 hours + 4 hours = 6 hours and made 2%2F10 +4%2F10 = 6%2F10  of the job in 6 hours.

So, the remaining job,  which was 1 - 6%2F10 = 4%2F10 = 2%2F5,  was done by Bobby.


Bobby worked 4 hours + 6 hours = 10 hours and completed  2%2F5  of the job.

Hence, Bob's rate of work was  %28%282%2F5%29%29%2F10 = 2%2F%285%2A10%29 = 2%2F50 = 1%2F25.


It means that Bobby takes  25 hours to print the entire manuscript alone.    ANSWER



                Algebra solution


Carlo's rate of work is 1/10 of the job per hour.

Let 'b' be the Bobby's rate of work.  It is unknown value now, for which we should set uo an equation and find it.


In 2 hours, Carlo made  2%2F10 = 1%2F5  of the job.

In the next 4 hours, Carlo made  4%2F10 = 2%2F5 of the job.

During these 4 hours, Bobby made 4b  parts of the job.

In next 6 hours, Bobby completed the job.


So, we write an equation for the whole job by summing these parts

    1%2F5 + 2%2F5 + 4b + 6b = 1.


Simplify and find 'b'

    3%2F5 + 10b = 1,

    10b = 1 - 3%2F5 = 2%2F5,

      b = %28%282%2F5%29%29%2F10 = 2%2F50 = 1%2F25.


Hence, Bobby needs 25 hours to make the whole job working alone.

We get the same answer.

Solved in simple manner in two different ways, for your better understanding.

This my solution teaches you on how to solve joint work problems using a conception of the rate of job.

It is MUCH SIMPLER than to follow the @mananth's approach.




Question 453010: can someone help me by tuesday plss :(?
solve the problem.
joanne mows the front yard in 40 min, while hope can mow the same yard in 50 min. how long would it take them, working together with two mowers, to mow the yard?

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
can someone help me by tuesday plss :(?
solve the problem.
joanne mows the front yard in 40 min, while hope can mow the same yard in 50 min. how long would it take them,
working together with two mowers, to mow the yard?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        In the post by @mananth, the internal calculations are presented in wrong form
        and can scare/confuse a reader. So I came to make a job as accurately as it should be done.


Joanne makes 1/40 of the job per minute.

Hope makes 1/50 of the job per minute.


Working together, the make  

    1%2F40 + 1%2F50 = 5%2F200 + 4%2F200 = 9%2F200

of the gob per minute.


Hence, they need  200%2F9 = 222%2F9  minutes to complete the job working together.


ANSWER.  The need 222%2F9 minutes to complete the job working together.

Solved correctly and presented in the normal form as it should be done.




Question 446848: a new machine can make 10,000 aluminum cans three times faster than an older machine. with both machines working, 10,000 cans be made in 9h. how long would it take the new machine, working alone, to make the 10,000 cans?
Found 3 solutions by MathTherapy, josgarithmetic, ikleyn:
Answer by MathTherapy(10806) About Me  (Show Source):
You can put this solution on YOUR website!
a new machine can make 10,000 aluminum cans three times faster than an older machine.  with both machines working,
10,000 cans be made in 9h. how long would it take the new machine, working alone, to make the 10,000 cans?

More LIKELY/Chances are, "three times faster......." should actually read,"three times as fast......"

If this is so, then:
Let time new machine takes to complete the job (make 10,000 aluminum cans), be T
Then, time old machine takes to complete the job (make 10,000 aluminum cans), is 3T
In 1 hour then, and working ALONE, new and old machines can do 1%2FT, and 1%2F%283T%29 of job, respectively
Since both, working together, can do the job in 9 hours, we then get: 1%2FT+%2B+1%2F%283T%29+=+1%2F9
                                                                        9 + 3 = T -- Multiplying by LCD, 9T

Time both take, working together, to complete the job (make 10,000 aluminum cans) = 12 hours

Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
"three times faster than"?
The work of doing 1 job is, making 10000 aluminum cans.

Old machine goes at the rate of 1%2F9 jobs per hour.
New land old machine together, 1%2F9%2B3%2F9=4%2F9 work rate, jobs per hour.

Time for the new machine on its own, some x hours.
1%2F9%2B1%2Fx=4%2F9
1%2Fx=4%2F9-1%2F9
1%2Fx=3%2F9=1%2F3

New machine needs 3 hours to do the one job, working on its own.

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
a new machine can make 10,000 aluminum cans three times faster than an older machine.
with both machines working, 10,000 cans be made in 9h. how long would it take the new machine,
working alone, to make the 10,000 cans?
~~~~~~~~~~~~~~~~~~~~~~


First, I want to say to the writer/(creator of this problem) and to the readers,
that this problem is good, interesting and educative. But it is formulated unprofessionally
in the post. As presented, its meaning is dark, and wording does not correspond to the rules
of using words in English. (Words sound anti-harmonic). So, I will re-formulate it in the right way:

    A new machine can make 3 aluminum cans in the same time as an older machine 
    makes 1 can. With both machines working together, 10,000 cans be made in 9h. 
    How long would it take the new machine, working alone, to make the 10,000 cans?


With this modified formulation, it is a standard classic entertainment problem,
which can be solved mentally, using reasoning and common sense.
See my solution below.


During this time interval of 9 hours, of 10,000 cans total, 7500 are made by the new machine 
and 2500 cans are made by the old machine. (it is because 7500 cans is three times 2500 cans).


So, we need to determine, how much time the new machine needs to produce 2500 cans.


But it is obvious: since the new machine produces 7500 cans in 9 hours, it will produce
one third, or 2500 cans in one third time of 9 hours, i.e. in 3 hours.


Thus, in all, the new machine needs 9 + 3 = 12 hours to produce 10,000 cans working alone.

Solved completely in this modified formulation.

--------------------

After this my solution, you can ignore the post by @mananth,
since it goes out the target.


/\/\/\/\/\/\/\/\/\/\/\/


Keep in mind that the "solution" in the post by @josgarithmetic is incorrect and irrelevant.

The best what you can do regarding the post by @josgarithmetic is to ignore it.




Question 446358: One person can do a certain job in six days, a second person can do the same job in two days, and a third person can do this job in three days. How many days will they take to do the job together?
Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
One person can do a certain job in six days, a second person can do the same job in two days,
and a third person can do this job in three days. How many days will they take to do the job together?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


        The solution and the answer in the post by @mananth are incorrect.
        I came to make the job correctly,  properly and accurately,  in a way as it  SHOULD  be done.


person  I   6 days
He does  1/6  of the job in 1 day

Person  II   2 days
He does  1/2  of the job in 1 day

Person  III   3 days
He does  1/3   of the job in 1 day

Together they will do

        1%2F6 + 1%2F2 + 1%2F3 = 2%2F12 + 6%2F12 + 4%2F12 = 12%2F12 = 1.

Together they make the entire job in one day
So they will take 1 day to complete the job.                 <<<---=== ANSWER

Solved correctly.




Question 730604: two taps take 8 hours to fill a tank. one tap takes 12 hours to do the same work. How long will the other tap take to fill the same tank?

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
Two taps take 8 hours to fill a tank. one tap takes 12 hours to do the same work.
How long will the other tap take to fill the same tank?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

The combined rate of work of the two taps is  1/12  of the tank volume per hour.


The individual rate of work of one tap is 1/12.


Hence, the individual rate of work of the other tap is the difference


    1%2F8 - 1%2F12 = use the common denominator 24 = 3%2F24 - 2%2F24 = 1%2F24  of the tank volume per hour.


It means that the other tap will take 24 hours to fill the tank working alone.

Solved.

This analysis using the rate of work is a simple and powerful method solving problems on joint work.


/\/\/\/\/\/\/\/\/\/\/\/\/


The answer in the post by @lynnlo is incorrect.
Simply ignore his post.




Question 730851: Zelda typed 531 words in 6 minutes.How many words can he type in 1 minute?

Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
Zelda typed 531 words in 6 minutes. How many words can he type in 1 minute?
~~~~~~~~~~~~~~~~~~~~~~~~~


To find the rate, divide the production amount by the time.




Question 734376: if a takes an old sweeper 30 hour to clean a street and takes a new and old sweepers together only 7.5 hours to clean the same street, then how long would it take for new sweeper to cleanse the same street?
Found 4 solutions by math_tutor2020, josgarithmetic, greenestamps, ikleyn:
Answer by math_tutor2020(3835) About Me  (Show Source):
You can put this solution on YOUR website!

There are many great answers by the other tutors.

Here's yet another approach.
Let's say the street length is 3000 feet in total.
The value 3000 doesn't matter and can be changed to any other number you want, since the final answer at the end will be the same.

The old sweeper does the full job in 30 hours when working alone.
The old sweeper's rate is (3000 ft)/(30 hr) = 100 feet per hour.

The new sweeper takes x hours to do the job when working alone.
The new sweeper's rate is 3000/x feet per hour.

Their combined rate is 100 + (3000/x) feet per hour.
This assumes that neither sweeper hinders the other.
Multiplying this combined rate by 7.5 hours should lead to the total 3000 feet needed to be cleaned.
7.5*( 100 + (3000/x) ) = 3000
which solves to x = 10

Therefore the new sweeper needs 10 hours to clean the entire street by itself.

Answer by josgarithmetic(39792) About Me  (Show Source):
You can put this solution on YOUR website!
n hours just the new sweeper alone
                RATE        TIME          JOB

OLD             1/30         30            1

NEW             1/n           n            1

BOTH           1/7.5          7.5          1

Rates of the two working together are simply additive.
highlight%281%2F30%2B1%2Fn=1%2F7.5%29
Solve.

Answer by greenestamps(13327) About Me  (Show Source):
You can put this solution on YOUR website!


An informal solution, using logical reasoning instead of the formal algebra shown in the response from the other tutor....

When the new sweeper joins the old one, the job is completed in 1/4 as much time (7.5 hours instead of 30), so it is as if there are now 4 of the old sweepers working.

That means the new sweeper does as much work as 3 of the old sweepers.

And since the old sweeper can do the job alone in 30 hours, the new sweeper can do the job alone is 1/3 as much time, which his 10 hours.

ANSWER: 10 hours


Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
if highlight%28cross%28a%29%29 it takes an old sweeper 30 hour to clean a street and takes a new and old sweepers together
only 7.5 hours to clean the same street, then how long would it take for new sweeper
to highlight%28cross%28cleanse%29%29 clean the same street?
~~~~~~~~~~~~~~~~~~~~~~~

From the problem, the combined rate of the old and the new sweepers is  1%2F7.5  of the job
per hour, when they work together,

while the rate of the old sweeper is  1%2F30  of the job per hour.


So, the rate of the new sweeper, when it works alone, is the difference

    1%2F7.5 - 1%2F30 = %2830-7.5%29%2F%287.5%2A30%29 = 21.5%2F%287.5%2A30%29 = 3%2F30 = 1%2F10

of the job per hour.


Hence, it will take 10 hours for the new sweeper to clean the street working alone.    ANSWER

Solved.

This method analyzing rate of work via fractions is very powerful and effective way solving such problems.




Question 732913: PumP A, working alone, can fill a tank in 3 hours, and pump B can fill tthe same tank in 2 hours. If the tank is empty to start and pump a is switched on for 1 hour, after which pump b is also switched on and the two work together, how many minutes will pump b have been working by the time the pool is filled?
Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
Pump A, working alone, can fill a tank in 3 hours, and pump B can fill the same tank in 2 hours.
If the tank is empty to start and pump A is switched on for 1 hour, after which pump B is also switched on
and the two work together, how many minutes will pump B have been working by the time the pool is filled?
~~~~~~~~~~~~~~~~~~~~~~~~


        On the way, the tank was transformed into the pool,
        but I will consider this transformation as playing words.


So, we know that pump A fills the tank in 3 hours = 180 minutes, working alone,
while pump B fills the tank in 2 hours = 120 minutes working alone.


When pump A worked alone during 1 hour, it filled 1/3 of the tank volume; 
so, 2/3 of the volume remained to fill.


Pump A fills  1/180  of the tank volume per minute;
pump B fills  1/120  of the tank volume per minute.


Working together, two pumps fill

    1%2F180 + 1%2F120 = 3%2F360 + 2%2F360 = 5%2F360 = 1%2F72

of the tank volume per minute.


And these two pumps should fill 2/3 of the tank volume.


It will take for them

    %28%282%2F3%29%29%2F%28%281%2F72%29%29 = %282%2A72%29%2F3 = 2*24 = 48 minutes.


ANSWER.  Pump B will work 48 minutes together with pump A to fill the tank. 

Thus the problem is just solved completely.

As you see from my post, my solution even does not require using equation:
it only requires manipulating with fractions.




Question 733071: You can stuff envelopes twice as fast as your friend. Together, you can stuff 6750 envelopes in 4.5 hours. How long would it take each of you working alone to complete the job?
Answer by ikleyn(53751) About Me  (Show Source):
You can put this solution on YOUR website!
.
You can stuff envelopes twice as fast as your friend. Together, you can stuff 6750 envelopes in 4.5 hours.
How long would it take each of you working alone to complete the job?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~


            It is so simple that can be easy solved mentally.


From the problem, you and your friend work as productive as 2+1 = 3 copies of your friend.


So, 3 persons, working as productive as your friend, will complete the job in 4.5 hours.


It means that your friend, working alone, will complete the job in 3*4.5 = 13.5 hours.


Hence, you, working alone, will complete the job in half of 13.5 hours, i.e. in

    13.5 / 2 = 6.75 hours = 6 hours and 45 minutes.

Solved.

The answer in the post by @lynnlo is incorrect.




Question 1210372: If painter A can paint a wall in one hour and painter B can paint the same wall in two hours, how long does it take for painter A and B to paint the same wall together?

Answer by math_tutor2020(3835) About Me  (Show Source):
You can put this solution on YOUR website!

Let's say the wall has an area of 300 square feet.
This value can be changed to anything you want, and the final answer will remain the same.

When working alone painter A can paint this wall in one hour, so his or her rate is 300/1 = 300 sq ft per hour.
The formula to use would be: speed = amountDone/time
Painter B has a rate of 300/2 = 150 sq ft per hour when working alone.

When the two work together, assuming neither worker slows down the other, we add their unit rates.
A+B = 300+150 = 450
Their combined rate is 450 sq ft per hour.

rate*time = amountDone
(450 sq ft per hr)*(x hours) = 300 sq ft
450*x = 300
x = 300/450
x = (2*150)/(3*150)
x = 2/3
It takes 2/3 of an hour if the two work together.
This is equivalent to 40 minutes because (2/3)*60 = 40.


Answer: 40 minutes


Older solutions: 1..45, 46..90, 91..135, 136..180, 181..225, 226..270, 271..315, 316..360, 361..405, 406..450, 451..495, 496..540, 541..585, 586..630, 631..675, 676..720, 721..765, 766..810, 811..855, 856..900, 901..945, 946..990, 991..1035, 1036..1080, 1081..1125, 1126..1170, 1171..1215, 1216..1260, 1261..1305, 1306..1350, 1351..1395, 1396..1440, 1441..1485, 1486..1530, 1531..1575, 1576..1620, 1621..1665, 1666..1710, 1711..1755, 1756..1800, 1801..1845, 1846..1890, 1891..1935, 1936..1980, 1981..2025, 2026..2070, 2071..2115, 2116..2160, 2161..2205, 2206..2250, 2251..2295, 2296..2340, 2341..2385, 2386..2430, 2431..2475, 2476..2520, 2521..2565, 2566..2610, 2611..2655, 2656..2700, 2701..2745, 2746..2790, 2791..2835, 2836..2880, 2881..2925, 2926..2970, 2971..3015, 3016..3060, 3061..3105, 3106..3150, 3151..3195, 3196..3240, 3241..3285, 3286..3330, 3331..3375, 3376..3420, 3421..3465, 3466..3510, 3511..3555, 3556..3600, 3601..3645, 3646..3690, 3691..3735, 3736..3780, 3781..3825, 3826..3870, 3871..3915, 3916..3960, 3961..4005, 4006..4050, 4051..4095, 4096..4140, 4141..4185, 4186..4230, 4231..4275, 4276..4320, 4321..4365, 4366..4410, 4411..4455, 4456..4500, 4501..4545, 4546..4590, 4591..4635, 4636..4680, 4681..4725, 4726..4770, 4771..4815, 4816..4860, 4861..4905, 4906..4950, 4951..4995, 4996..5040, 5041..5085, 5086..5130, 5131..5175, 5176..5220, 5221..5265, 5266..5310, 5311..5355, 5356..5400, 5401..5445, 5446..5490, 5491..5535, 5536..5580, 5581..5625, 5626..5670, 5671..5715, 5716..5760, 5761..5805, 5806..5850, 5851..5895, 5896..5940, 5941..5985, 5986..6030, 6031..6075, 6076..6120, 6121..6165, 6166..6210, 6211..6255, 6256..6300, 6301..6345, 6346..6390, 6391..6435, 6436..6480, 6481..6525, 6526..6570, 6571..6615, 6616..6660, 6661..6705, 6706..6750, 6751..6795, 6796..6840, 6841..6885, 6886..6930, 6931..6975, 6976..7020, 7021..7065, 7066..7110, 7111..7155, 7156..7200, 7201..7245, 7246..7290, 7291..7335, 7336..7380, 7381..7425, 7426..7470, 7471..7515, 7516..7560, 7561..7605, 7606..7650, 7651..7695, 7696..7740, 7741..7785, 7786..7830, 7831..7875, 7876..7920, 7921..7965, 7966..8010, 8011..8055, 8056..8100, 8101..8145, 8146..8190, 8191..8235, 8236..8280, 8281..8325, 8326..8370, 8371..8415, 8416..8460, 8461..8505, 8506..8550, 8551..8595, 8596..8640, 8641..8685, 8686..8730, 8731..8775, 8776..8820, 8821..8865, 8866..8910, 8911..8955