one machine plows a field in 4 days ,other does in 6 days.how long does it take using both machine?
Answer by
CubeyThePenguin(3113)
(
Show Source
):
You can
put this solution on YOUR website!
Machine A plows 1/4 of the field in a day.
Machine B plows 1/6 of the field in a day.
Combined: 1/4 + 1/6 = 5/12 ---> 12/5 days to plow the field