| Question 996086:  It takes 14 electricians 18 days to wire a new housing subdivision. How many days would it take 24 electricians to do the same job?
 Answer by Theo(13342)
      (Show Source): 
You can put this solution on YOUR website! rate per person * number of people * time = quantity. 
 rate per person is what you want to find first.
 number of people is 14 electricians.
 time is 18 days.
 quantity is 1 job, the job being to wire a new housing subdivision.
 
 formula becomes:
 
 rate per person * 14 * 18 = 1
 
 rate per person = 1 / (14 * 18).
 
 now, if you have 24 electricians working at the same rate per person, then you get:
 
 rate per person * number of people * time = quantity becomes:
 
 1 / (14 * 18) * 24 * time = 1
 
 solve for time to get time = (14 * 18) / 24 = 252 / 24 = 10.5
 
 it would take 24 electricians 10.5 days to do the same job working at the same rate per person.
 
 
 | 
  
 | 
 |  |  |