Question 947903: A Certain Job Can Be Done By 8 Men In 20 Days. After 5 Days, 3 Men Left The Job. How Long Would It Take The Remaining Men To Finish The Job?

Found 2 solutions by Theo, Fombitz:
Answer by Theo(13342) About Me  (Show Source):
You can put this solution on YOUR website!
the general formula is:
r*p*t = q
r is the rate that each person works at.
p is the number of persons.
t is the amount time.
q is the quantity of work.

in this problem:
r is what you want to find
p is 8
t is 20 days
q is 1 job

in this problem, r*p*t = q becomes r*8*20 = 1
solve for r to get r = 1/160.
this means that 1 person can complete 1/160 of the job in 1 day.

if you replace r in the equation we just worked, you would get r*p*t = q becomes 1/160 * 8 * 20 = 1 which becomes 160 / 160 = 1 which becomes 1 = 1.

this confirms the solution for r is correct.

not that you know r, you can solve the problem.

you are told that, after 5 days, 3 men left the job.

you can use r and p and t to solve for q.

first you want to find how much of the job was finished by the 8 original men in 5 days.

r*p*t = q becomes 1/160*8*5 = q
solve for q to get q = 40/160 which reduces to 1/4.

8 men will complete 1/4 of the job in 5 days.

that means that 3/4 of the job still remains to be done.

the 8 men are working at the rate of 1/160 of the job per day per person. This rate per person remains constant throughout, regardless of the number of persons working.


3 men leave the job, so you are left with 5 men to complete it.

you want to know how long it will take those 5 men to complete the remaining 3/4 of the job.

the general formula of r*p*t = q becomes 1/160*5*t = 3/4

the rate per person is still the same at 1/160 of the job in one day.
the number of people is now 5.
t is what you want to find.
q is equal to the remaining 3/4 of the job that still needs to be done.

1/160*5*t = 3/4 is the equation you now need to solve for t.

solve for t to get t = 24 days

the remaining 5 people will finish the remaining 3/4 of the job in 24 additional days.

the total number of days to finish the job is therefore 5 + 24 = 29 days.

to confirm, do the following:

the total job required 29 days.
5 days with 8 people working and 24 days with 5 people working.
the rate per person is the same at 1/160 as we had previously calculated.

1/160 * 8 * 5 = 40/160 = 1/4 of the job.
1/160 * 5 * 24 = 120/160 = 12/16 = 3/4 of the job.
1/4 and 3/4 equal the whole job.

the numbers check out and the number of days required for the 5 men to complete the job is 24 days.



Answer by Fombitz(32388) About Me  (Show Source):
You can put this solution on YOUR website!
Rate*Time=Output
Assume each man works at the rate, R.
8R%2A20=100
R=100%2F160
R=5%2F8
So then after three days the amount of output is,
8R%2A3=8%285%2F8%29%2A3=15
So the amount of output that remains to be done is,
100-15=85
So now only 5 men working to output the remaining 85,
5R%2At=85
R%2At=17
%285%2F8%29t=17
t=136%2F5=27%261%2F5days