SOLUTION: If it takes 6 men to complete a job in 12 days, how many men would it take to complete the same job in 18 days?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: If it takes 6 men to complete a job in 12 days, how many men would it take to complete the same job in 18 days?      Log On


   



Question 911696: If it takes 6 men to complete a job in 12 days, how many men would it take to complete the same job in 18 days?
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
man-days 6*12=72
new number of days=18=18
man days needed/days 72/18= 4 workers needed