SOLUTION: P can do a piece of work in 20 days and Q in 24 days. find how much time will they take to complete the work if they work alternately starting with P ?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: P can do a piece of work in 20 days and Q in 24 days. find how much time will they take to complete the work if they work alternately starting with P ?
Log On
Question 908139: P can do a piece of work in 20 days and Q in 24 days. find how much time will they take to complete the work if they work alternately starting with P ? Answer by richwmiller(17219) (Show Source):