SOLUTION: 40 rooms of a school are to be painted in 2 weeks by 30 workers. only 20 workers show up.Find the time taken to complete the task

Algebra ->  Rate-of-work-word-problems -> SOLUTION: 40 rooms of a school are to be painted in 2 weeks by 30 workers. only 20 workers show up.Find the time taken to complete the task      Log On


   



Question 889592: 40 rooms of a school are to be painted in 2 weeks by 30 workers. only 20 workers show up.Find the time taken to complete the task
Answer by richwmiller(17219) About Me  (Show Source):
You can put this solution on YOUR website!
30*2=60 worker weeks
60/20=3 weeks