Question 849367: Twenty people working 9 hours per day are needed to complete a large sorting job within ten days. How many hours per day would eighteen people need to have worked to complete the job within the same time? Found 2 solutions by richwmiller, josmiceli:Answer by richwmiller(17219) (Show Source):
You can put this solution on YOUR website! 20*9*10=180*10 worker hours for ten days
180/18=10
They would have to work 10 hours a day for ten days
You can put this solution on YOUR website! 1/10 as many people would take 10 times
longer to do the same job, so
------------------------------------------- people take
hours to do the same job
--------------------------------------------
The rate that the 20 people work is ( 1 job ) / ( 90hrs )
=
The rate that the 2 people work is ( 1 job ) / ( 900 hrs )
=
----------------------------------------------
Let ( 1 job ) / ( h hours ) = = the rate that
18 people work
----------------
I can then say:
Multiply both sides by
---------------
( 100 hrs ) / ( 10 days ) = 10 hrs / day
So, 18 people need to work 10 hrs a day to
finish the job in 10 days