SOLUTION: A can do a piece of work in 80 days and B in 64 days and C in 160 days. All begin to do it altogether but A leaves after 20 days and B leaves after 15 days before completion of the
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A can do a piece of work in 80 days and B in 64 days and C in 160 days. All begin to do it altogether but A leaves after 20 days and B leaves after 15 days before completion of the
Log On
Question 847000: A can do a piece of work in 80 days and B in 64 days and C in 160 days. All begin to do it altogether but A leaves after 20 days and B leaves after 15 days before completion of the work. How long did the work last?? Answer by josmiceli(19441) (Show Source):
You can put this solution on YOUR website! What fraction of the work does A
get done in 20 days?
What fraction does B get done in
15 days?
The fraction of the work that is left is:
C has to do this fraction of the work in
the remaining days,
---------------------------
C's rate of working is ( i job ) / ( 160 days )
I can say:
The work lasts 82.5 days
------------------------
Check my math, and you might want
a 2nd opinion on this , too