SOLUTION: If it takes 8 men 9 hours to dig a hole in 20 meters deep,how long would it take 10 men to dig a hole if they work at the same rate?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: If it takes 8 men 9 hours to dig a hole in 20 meters deep,how long would it take 10 men to dig a hole if they work at the same rate?
Log On
You can put this solution on YOUR website! If it takes 8 men 9 hours to dig a hole in 20 meters deep,
Find the number of man-hours required to do the job
8 * 9 = 72 man-hrs
:
how long would it take 10 men to dig a hole if they work at the same rate?
let h = no. of hrs for 10 men do the same job
10h = 72
h = 7.2 hrs