Question 823903: 12 men take 27 hours to paint a house. Given that all the men work at the same rate, find how long it will take 9 men to paint the same house. I would really appreciate your time and effort if you could help me with this question. I really don't know a method to solve it. Thanks! Found 2 solutions by josgarithmetic, richwmiller:Answer by josgarithmetic(39617) (Show Source):
You can put this solution on YOUR website! If only 1 of the men, then the work rate is of the group of 12 men. This means, 1 man goes at the rate of houses per hour. The question is about the rate for 9 men:
Knowing their rates are additive, houses per hour, which using the reciprocal, is 36 hours to paint one house.
You can put this solution on YOUR website! find out the man hours needed to paint the house
12*27=324 man hours needed to paint the house
there are only 9 men available to do the 324 man hours
324/9=36 hours for 9 men