Question 798942: A piece of work can be done by 40 days by 25 men. After 16 days, 13 men are transferred. In how many days can the remaining men finish the work?
Answer by Finavon(81) About Me  (Show Source):
You can put this solution on YOUR website!
N days remaining
work=40*25 = (16*25) + (12*N)
1000 = 400 + 12N
+N+=+%281000-400%29%2F12+=+600%2F12+=+50+
Work takes 50 further days
Check: (16*25) + (12*50) = 400 + 600 = 1000