SOLUTION: A group of men can do a job in as many days as there are men in the group. If the number of men is increased by 10, the number of days to do the job will be decreased by 8. Find th

Algebra ->  Rate-of-work-word-problems -> SOLUTION: A group of men can do a job in as many days as there are men in the group. If the number of men is increased by 10, the number of days to do the job will be decreased by 8. Find th      Log On


   



Question 775856: A group of men can do a job in as many days as there are men in the group. If the number of men is increased by 10, the number of days to do the job will be decreased by 8. Find the number of men in the group.
Answer by mananth(16946) About Me  (Show Source):
You can put this solution on YOUR website!
let the number of men be x
No of days taken = x
x men will do 1/x of the job in 1 day
x+10 men
number of days = x-8
(x-8)/(x-10) of the job in 1 day
%28x-8%29%2F%28x%2B10%29+=+1%2Fx
x^2-8x=x+10
x^2-9x-10=0
x^2-10x+x-10=0
x(x-10)+1(x-10)=0
(x-10)(x+1)=0
x=10 OR -1
ignore negative
x=10====> number of men