Question 705817: X can do (1/4) of work in 10 days. Y can do 40% of the work in 40 days and Z can do (1/3) of the work in 13 days. Who will complete the work first?
Answer by MathLover1(20849) About Me  (Show Source):
You can put this solution on YOUR website!

if X can do %281%2F4%29 of work in 10 days, means X need 4 times more days to complete the whole work: so, whole work will be done by in 10%2A4=40 days

if Y can do 40% =40%2F100=0.40 of the work in 40 days; so,whole work will be done by in 0.40d=40...=>...d=40%2F0.40 ...=>...d=100 days

and, if Z can do %281%2F3%29 of the work in 13 days, means Z need 3 times more days to complete the whole work:
so, whole work will be done by in 13%2A3=39 days
Therefore, Z will complete the work first.