SOLUTION: It takes 16 painters 7 hours to paint a building, how many painters working at the same rate are needed to paint the building in 4 hours?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: It takes 16 painters 7 hours to paint a building, how many painters working at the same rate are needed to paint the building in 4 hours?
Log On
Question 665589: It takes 16 painters 7 hours to paint a building, how many painters working at the same rate are needed to paint the building in 4 hours? Answer by ewatrrr(24785) (Show Source):