SOLUTION: 6 children and 2 men complete a certain peice of work in 6 days ,each child takes twice the time teken by a man to fifnish the work ,in how many days will 6 men ll finish the work?

Algebra ->  Rate-of-work-word-problems -> SOLUTION: 6 children and 2 men complete a certain peice of work in 6 days ,each child takes twice the time teken by a man to fifnish the work ,in how many days will 6 men ll finish the work?      Log On


   



Question 657201: 6 children and 2 men complete a certain peice of work in 6 days ,each child takes twice the time teken by a man to fifnish the work ,in how many days will 6 men ll finish the work?
Answer by KMST(5328) About Me  (Show Source):
You can put this solution on YOUR website!
THE FIFTH GRADER SOLUTION:
If "each child takes twice the time taken by a man to finish the work", then 2 children do the same work as 1 man, and 6 children would do the work of 3 men.
Then, 6 children and 2 men would do the same work as 3 men and another 2 men, which adds up to 5 men.
The amount of work done was 5 men times 6 days or 5%2A6 man-days.
Obviously, 6 men working highlight%285%29 days will also finish the same 5%2A6 man-days job.

WHAT THE TEACHER EXPECTS,
I am not exactly sure, because there are many problem-solving recipe books.
I do not know what recipe your teacher uses, but I will try my best guess.
The amount of work done by a person or a group (or some sort of machine, divided by the time worked is the rate of work.
rate=work%2Ftime
once we know the rate of work, we can calculate work done over a given period of time, or time required to finish a given amount of work
If one man would take t days to finish the job by himself, then a child would take 2t days.
A man's rate of work would be 1%28job%29%2F%28t%28days%29%29=1%2Ft, in jobs per day.
(We could call that the rate of work of a man, r=1%2Ft, in jobs per day, and we would save ourselves from writing so many denominators).
A child's rate of work would be 1%28job%29%2F%282t%28days%29%29=1%2F2t
The rate of work for a group would be found adding the rates for all the members of the group.
The rate of work for 6 men would be 6%2A%281%2Ft%29=6%2Ft.
The rate of work for 2 men and 6 children would be
2%2A%281%2Ft%29%2B6%2A%281%2F2t%29=2%2Ft%2B3%2Ft=5%2Ft
The group of 2 men and 6 children completed 1 job in 6 days, so
6%2A%285%2Ft%29=1job
The group of 6 mean would complete the same job in x days, so
x%2A%285%2Ft%29=6%2A%285%2Ft%29
Multiplying both sides times t, which we know is not zero,
x%2A%285%2Ft%29=6%2A%285%2Ft%29 --> 5x=6%2A5 --> highlight%28x=5%29 days.