SOLUTION: if 6 roofers take 2 days to put on a new roof, how long would it take 4 roofers to do the same job, assuming they each work at the same rate?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: if 6 roofers take 2 days to put on a new roof, how long would it take 4 roofers to do the same job, assuming they each work at the same rate?
Log On
Question 586466: if 6 roofers take 2 days to put on a new roof, how long would it take 4 roofers to do the same job, assuming they each work at the same rate? Found 2 solutions by ankor@dixie-net.com, eschwartz:Answer by ankor@dixie-net.com(22740) (Show Source):
You can put this solution on YOUR website! if 6 roofers take 2 days to put on a new roof, how long would it take 4 roofers to do the same job, assuming they each work at the same rate?
:
Find the number of man-days to do the job
6 * 2 = 12 man-days
:
"how long would it take 4 roofers to do the same job,"
let d = no. of days for 4 men to do it
4d = 12
d = 12/4
d = 3 days
You can put this solution on YOUR website! You could also say like this:
You now have of the work force, so you will need the time.
Workers are:
Time required is: