Question 529408: When painting the walls of an art museum, the painters found that it took 5 men to paint 4 walls in 6 hours. Then, 9 more men were added to the job. How many hours would it take them to do 28 rooms?
Answer by lwsshak3(11628) About Me  (Show Source):
You can put this solution on YOUR website!
When painting the walls of an art museum, the painters found that it took 5 men to paint 4 walls in 6 hours. Then, 9 more men were added to the job. How many hours would it take them to do 28 rooms?
**
It took 5*6=30 man-hours to complete painting 4 walls or one room
28 rooms will require 30*28=840 man hours
men on job=5+9=13
Hours to paint 28 rooms=840/13≈64.62 hrs