You can put this solution on YOUR website! If it takes 5 men 8 weeks to build 2 barns, how long will it take 12 men to build 15 barns?
**
It takes 5*8=40 man-weeks to build 2 barns
To build 15 barns it would take 15/2*40=300 man-weeks
300 man-weeks/12 men=25 weeks
ans:
It would take 12 men 25 weeks to build 15 barns