You can put this solution on YOUR website! if 20 men can do a piece of work in 8 days,
20 * 8 = 160 man-days to complete the job
:
then how many men can finish the same work in 10 days?
let m = no. of men required to do the job in 10 days
10m = 160
m =
m = 16 men