SOLUTION: paul paint his house in 12 days if works 8hr/day. how many day he will take to paint if he works 6hr/day

Algebra ->  Rate-of-work-word-problems -> SOLUTION: paul paint his house in 12 days if works 8hr/day. how many day he will take to paint if he works 6hr/day       Log On


   



Question 476573: paul paint his house in 12 days if works 8hr/day. how many day he will take to paint if he works 6hr/day

Answer by Engg.N Magampon(6) About Me  (Show Source):
You can put this solution on YOUR website!
total time of work= (total no. of days worked)(time of work per day)
TW= DW x TWd
=12days x 8hours/day
=96hours
apply the formula above then derive it
96hours =DW x 6hours/day
DW=96 hours/6hours/day
DW=16 days
Paul will finish painting his house in 16 days if he worked 6hours/day