SOLUTION: a mason can construct a retaining wall in 10 h. with the mason's apprentice assisting, the task takes 6 h. how long would it take the apprentice, working alone, to construct the wa
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: a mason can construct a retaining wall in 10 h. with the mason's apprentice assisting, the task takes 6 h. how long would it take the apprentice, working alone, to construct the wa
Log On
Question 446852: a mason can construct a retaining wall in 10 h. with the mason's apprentice assisting, the task takes 6 h. how long would it take the apprentice, working alone, to construct the wall? Answer by robertb(5830) (Show Source):