| Question 233456:  If 6 men can do a job in 4 hours, how many hours will it take 8 men to do it-and why?
 Answer by Alan3354(69443)
      (Show Source): 
You can put this solution on YOUR website! If 6 men can do a job in 4 hours, how many hours will it take 8 men to do it-and why? ---------------
 The job is 24 man-hrs (6*4)
 24 man-hrs/8 men = 3 hours.
 ----------------------------
 As for why, because that's the answer, that's how long it takes.
 | 
  
 | 
 |  |  |