|
Question 1208171: If 8 men take 12 days to assemble 16 machines, how many days will it take 15 men to assemble 50 machines
Found 5 solutions by ikleyn, josgarithmetic, greenestamps, Edwin McCravy, mccravyedwin: Answer by ikleyn(52754) (Show Source): Answer by josgarithmetic(39613) (Show Source): Answer by greenestamps(13195) (Show Source):
You can put this solution on YOUR website!
You have, so far, two responses showing very different methods for solving the problem.
There are numerous other methods; below is a solution by the method I find easiest.
The problem asks for how many days it will take. So start with the given number of days, 12, and multiply it by factors based on how the values of the other parameters change.
The given scenario has 8 men; the new scenario has 15 men. More men means fewer days, so the number of days changes by a factor of 8/15.
The given scenario has 16 machines; the new scenario has 50. More machines to make means more days, so the number of days changes by a factor of 50/16.
The calculation is then

Cancel some common factors before performing the multiplication:

ANSWER: 20 days
Answer by Edwin McCravy(20054) (Show Source): Answer by mccravyedwin(405) (Show Source):
You can put this solution on YOUR website!
Here is what I now believe is the best way to do this kind of problem, and how
to think it out,
I believe it should be taught this way:
I will use COMBINED VARIATION, defined as follows:
Combined variation describes a situation where a variable depends on two (or
more) other variables, and varies directly with some of them and varies
inversely with others (when the rest of the variables are held constant).
We are asked for TIME REQUIRED, so let's see how TIME varies with each of the
other two variables, the number of workers and the number of jobs.
Time required varies DIRECTLY with the number of jobs IF the number of workers
remains constant.
(The more jobs, the more time required. The less jobs, the less time required.
Obvious!)
Time required varies INVERSELY with the number of workers IF the number of jobs
remains constant. (The more workers, the less time required. The less workers,
the more time required. Obvious!)
Therefore, when we let everything vary, we have a case of combined variation
So to state the combined variation involved:
Time required varies directly with the number of jobs
and inversely with the number of workers.
Let T = time required, J = number of jobs, W = number of workers.
8 men take 12 days to assemble 16 machines
Solve for k:
Substitute 6 for k:
how many days will it take 15 men to assemble 50 machines?
answer: 20 days.
Edwin
|
|
|
| |