So it would take 1 person 6 times as long, or 72 days. (since 6×12=72)How long would it take 4 people to paint the same wall?
Only 1/4 as long, or 18 days. (since 72×(1/4)=18). Edwin
The entire job is 6*12 = 72 working days (man-days). With 4 workers, the job will be completed in= 18 days. ANSWER