Question 1150748: Three workers have to do a certain job. The first worker can finish the job in 8 hours. The second worker can finish the job in 4 hours. The third worker can also finish the job in 4 hours. How long will it take the three workers to finish the job if they work together? Found 2 solutions by ikleyn, greenestamps:Answer by ikleyn(52776) (Show Source):
In one hour, they can do = of the job working together.
Hence, they can complete the entire job in hours = 8*12 minutes = 96 minutes = 1 hour and 36 minutes.