Question 1129107: Working together, it takes two computers 20 minutes to send out a company's email. If it takes the slower computer 45 minutes to do the job on its own, how long will it take the faster computer to do the job on its own? Answer by greenestamps(13198) (Show Source):
The two computers together do 1/20 of the job each minute; the slower computer does 1/45 of the job each minute. So the fraction of the job done by the faster computer each minute is
So the time required for the faster computer to do the job alone is 36 minutes.