SOLUTION: A Foreman needs 14 workers to complete a certain task in 16 days. However,
after 8 days, the engineer instructed him to complete the task in following 4 days to
allow other teams
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: A Foreman needs 14 workers to complete a certain task in 16 days. However,
after 8 days, the engineer instructed him to complete the task in following 4 days to
allow other teams
Log On
Question 1125787: A Foreman needs 14 workers to complete a certain task in 16 days. However,
after 8 days, the engineer instructed him to complete the task in following 4 days to
allow other teams enough time. How many additional workers does the foreman
need to request for?
a. 6
b. 10
c. 9
d. 8 Found 2 solutions by josgarithmetic, ikleyn:Answer by josgarithmetic(39617) (Show Source):
1. After working 8 days, the team of 16 workers completes one half of the job; hence, one half of the job remains to do.
2. If 14 workers complete the job in 16 days, then 14 workers would complete the remaining half of the job in 8 days.
Since the requirement is to complete the remaining half of the job in 4 days,
28 workers are needed for it, in all.
3. Hence, 28-14 = 14 additional workers should be employed.