SOLUTION: 8 workers working at the same rate can finish some work in 16 days.After working for 4 days,2 workers felt sick and never turned back.How many days did the they take to complete th
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: 8 workers working at the same rate can finish some work in 16 days.After working for 4 days,2 workers felt sick and never turned back.How many days did the they take to complete th
Log On
Question 1125204: 8 workers working at the same rate can finish some work in 16 days.After working for 4 days,2 workers felt sick and never turned back.How many days did the they take to complete the work? Answer by josgarithmetic(39617) (Show Source):
-------------------------------------------------
Eight workers, each working at the same rate, can finish a quantity of work in 16 days. After working for 4 days,2 workers felt sick and never returned back. How many days did the the remaining workers take to complete the work?
-------------------------------------------------
r, the rate of 1 worker , using "a quantity of work" as 1 whole piece of work.
The two separate numbers of workers for different time quantities, x for the unknown time quantity:
x=16
---------------------------------------------------
A different try:
After the full eight worked for 4 days, of the job still needed to be done. That is, 6 workers must work for x days to complete of the job.