SOLUTION: a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work how many men required to complete full work?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work how many men required to complete full work?
Log On
Question 1108786: a contractor contract to build a house in 30 days after 20 days 10 men complete 1/3 work how many men required to complete full work? Answer by josgarithmetic(39617) (Show Source):
You can put this solution on YOUR website! ----------------------------------------------
... After 20 days 10 men complete 1/3 work.
----------------------------------------------
r, one-man rate
Amount of job done was ;
-----------------------------------------------------------
contract to build a house in 30 days;
how many men required to complete full work?
-----------------------------------------------------------
Need to do still, of the job, and use additional n men with the same 10, and need to do this amount of work in 10 days.
-
------------30 more men needed, to complete the work.