Question 1065584: a crew of four workers is working on installing a roof on a house. The work is equally divided among the crew and work is scheduled to be completed in 4 days. What fraction of the whole roof is to be completed by each worker everyday to finish the project on time? Answer by josgarithmetic(39617) (Show Source):