SOLUTION: 15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how many days the work be finished?
Algebra ->
Rate-of-work-word-problems
-> SOLUTION: 15 men can do a work in 210 days.if 15 additional men engaged every after 10 days, in how many days the work be finished?
Log On
You can put this solution on YOUR website! 15 men can do a work in 210 days.
Find how many man-days required to complete the job
15 * 210 = 3150 man days
:
if 15 additional men engaged every after 10 days, in how many days the work be finished?
:
Days - manhr - Tot manhr
10 - 15*10=150 - 150
20 - 30*10=300 - 450
30 - 45*10=450 - 900
40 - 60*10=600 - 1500
50 - 75*10=750 - 2250
60 - 90*10=900 - 3150 man-hrs complete the job
:
It will take 60 days and a total of 90 men will be working then