SOLUTION: Four processes are involved in assembling a certain product and they can be preformed in any order. The management wants to test each order to determine which is the least time con

Algebra ->  Permutations -> SOLUTION: Four processes are involved in assembling a certain product and they can be preformed in any order. The management wants to test each order to determine which is the least time con      Log On


   



Question 1033080: Four processes are involved in assembling a certain product and they can be preformed in any order. The management wants to test each order to determine which is the least time consuming. How many different orders will have to be tested?
Answer by ikleyn(52776) About Me  (Show Source):
You can put this solution on YOUR website!
.
Four processes are involved in assembling a certain product and they can be preformed in any order.
The management wants to test each order to determine which is the least time consuming. How many different orders will have to be tested?
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

4! = 4*3*2*1 = 24.