If 6 men can do piece of work in 20days,how many extra men should engaged to do job in 15 days?
Answer by
josgarithmetic(39617)
(
Show Source
):
You can
put this solution on YOUR website!
r, the work rate for 1 man. The same 1 job is to be done in either case.
Let n be the number of additional men.
; and just solve for n.